City continues 7th Street extension effort

Winchester officials say the long-planned project remains important despite delays

|

Estimated time to read:

3–5 minutes
Trucks from I-64 and Ky. 626 still go down Magnolia Street to the Freeman Corporation, which makes hardwood veneer. The company owns the part of the street from the CSX railroad tracks.
Trucks from I‑64 and Ky. 626 still go down Magnolia Street to the Freeman Corporation, which makes hard­wood veneer. The com­pa­ny owns the part of the street from the CSX rail­road tracks. (Randy Patrick)

Big trucks no longer rum­ble down 7th Street, leav­ing a wake of grav­el dust that set­tles on cars and hous­es in the qui­et neigh­bor­hood. That’s because their des­ti­na­tion, Gate Precast Company, closed five years ago. 

However, the City of Winchester is still pur­su­ing a street exten­sion project that has been a pri­or­i­ty for decades because truck traf­fic is still an issue along anoth­er near­by res­i­den­tial street. 

Large trucks use Magnolia Street off Maple to access the Freeman Corporation’s plant, which man­u­fac­tures hard­wood veneer. 

In addi­tion to alle­vi­at­ing the truck traf­fic prob­lem, offi­cials believe the project would ben­e­fit the city by spurring com­mer­cial devel­op­ment near the inter­sec­tion of Maple Street and Veterans Memorial Parkway, just south of the I‑64 interchange. 

And anoth­er rea­son they want to con­tin­ue the project is that the city and state gov­ern­ments have already spent too much time and mon­ey on the project not to fin­ish it. 

City Manager Mike Flynn, when asked recent­ly about the con­cern of a for­mer city offi­cial that the city needs to use the mon­ey or it will lose it, said he doesn’t think that will happen. 

“We’re so far down the line now,” he said. “You nev­er say nev­er, but we’re at a point in the project where nei­ther the state nor the city wants to lose the funds that have been expend­ed on this project, and they’re going to act accordingly.” 

Truck traffic in residential neighborhoods on the northwest side of Winchester near Maple Street was the original reason for the 7th Street extension project.
Truck traf­fic in res­i­den­tial neigh­bor­hoods on the north­west side of Winchester near Maple Street was the orig­i­nal rea­son for the 7th Street exten­sion project. (Randy Patrick)

Currently, the project is sched­uled to be com­plet­ed in December 2027, but Flynn said that, real­is­ti­cal­ly, it will prob­a­bly take at least anoth­er year. 

It is also like­ly to end up cost­ing more than the orig­i­nal $4.45 mil­lion esti­mate, he said. 

When the project first began, the main con­cern was that grav­el trucks had to go through the nar­row 7th Street neigh­bor­hood to Gate Precast’s plant, which man­u­fac­tured pre­fab­ri­cat­ed con­crete for struc­tures. But in 2021, the com­pa­ny announced it was clos­ing the plant at 101 N. 7th St., one of Winchester’s old­est fac­to­ries, because it was con­sol­i­dat­ing its Winchester oper­a­tions with those of its oth­er nine loca­tions, at Ashland City, Tenn. 

However, fund­ing had already been allo­cat­ed for the 7th Street exten­sion, with the city’s match expect­ed to be $800,000. The city bud­get­ed $300,000 but antic­i­pat­ed also using $500,000 from the state’s Rural and Secondary Road Program dis­cre­tionary fund. 

The state approved $240,000 for the orig­i­nal project design, which was com­plet­ed on a pre­lim­i­nary basis. 

Working with the Transportation Cabinet’s District 7 office and Palmer Engineering, offi­cials got CSX to approve a rail­road track cross­ing and got all the per­mits required from state agencies. 

In ear­ly 2021, it was deter­mined that there was a $246,500 short­fall and that the city would cov­er that cost. 

At that time, Flynn said, it was deter­mined that a sig­nif­i­cant part of the cost of the project was asso­ci­at­ed with relo­cat­ing water and sew­er lines, gas lines, and oth­er infrastructure. 

“It was well over half of the cost of the project,” he noted. 

So, in 2024, the city com­mis­sion asked Palmer Engineering to look at a redesign of the project to elim­i­nate some of that relo­ca­tion work, and the com­ple­tion date was extend­ed to Dec. 31, 2027. 

Gate Precast Company has closed, but for many years, big trucks rolled down 7th Street, causing noise and a gravel dust problem for neighbors.
Gate Precast Company has closed, but for many years, big trucks rolled down 7th Street, caus­ing noise and a grav­el dust prob­lem for neigh­bors. (Randy Patrick)

Palmer Engineering is work­ing to obtain the FEMA flood study infor­ma­tion that is required, and they’re hav­ing to recre­ate part of that to sub­mit to “the prop­er author­i­ties,” Flynn said. 

The city man­ag­er said the District 7 office has reviewed the right-of-way plans, and Palmer is con­tin­u­ing to work on the drainage analy­sis and get appraisals for the right-of-way acquisition. 

Never miss a thing with our FREE weekly newsletter.

The hard part of the puz­zle, Flynn said, is going through the legal process nec­es­sary to obtain the right-of-way nec­es­sary to extend the corridor. 

It was made even hard­er, he said, by changes in the last leg­isla­tive ses­sion regard­ing emi­nent domain and reg­u­la­tions, which length­en the process. 

“If we can get the right-of-way, I believe the project should move along expe­di­tious­ly,” he said. 

From the city government’s per­spec­tive, Flynn said, the exten­sion “is still, I think, a very much need­ed state project.” 

Please share this story!